ULTILAYER

Time saving road upgrade to install sustainable cycle-way

A307, Kingston Upon Thames


Image

Client

Royal Borough of Kingston Upon Thames (RBK)


Contractor

Kier/ELM Surfacing


Location type

Main road


Completion

November 2018



The challenge

The ‘Mini Hollands’ programme is a part of the Mayor of London’s Healthy Streets agenda. The aim is to encourage Londoners to walk or cycle on short journeys, instead of using their car. Kingston upon Thames was one of three London Boroughs awarded £30 million to improve its infrastructure through the council’s Go Cycle project. In the first phase of the project, ELM Surfacing were selected by the main contractor, Kier, to improve the road and cycle lane along Kingston High Street (A307). It was important to demonstrate long term value for this investment. Given the high volumes of traffic using this route, it was also important to keep road closures and delays to a minimum. Originally, a 40mm deep 10mm PSV 68 surface course had been specified along with a 60 mm deep 20mm HDM binder course.



Our solution

Having used Tarmac’s ULTILAYER asphalt on other schemes, ELM Surfacing proposed it as a way of value engineering this project. ULTILAYER combines a high performance Polymer Modified Binder (PMB) and selected aggregates for a highly flexible, strong and durable asphalt suitable for long term trafficking. ULTILAYER would be used as a 20mm binder course laid 60mm deep and a 14mm ULTILAYER surface course laid 40mm deep using 68 PSV aggregate. They would both be laid in a single shift enabling work to be completed overnight (between 20:00hrs – 05:00hrs) rather than through a block road closure programme that would have caused major disruption to local residents. In another section of the works, where a lower PSV was allowed, they proposed 130 tonnes of 14mm ULTILAYER S surface course with a 60 PSV using carbon neutral, steel slag aggregate which is considerably more durable than the hard stone usually used in road construction.



Results and benefits

ELM Surfacing planed off the existing road surface and laid 175 tonnes of 20mm ULTILAYER binder course and 260 tonnes of 14mm ULTILAYER surface course with the required 68 PSV. During the works ELM reduced the width of the vehicular carriageway to accommodate the new cycle lanes, moved the crown of the road and installed speed tables as a means of traffic calming. The cost saving allowed a final section of the high street to be completed which had previously been omitted due to budget constraints. Both the client and supply chain partners were delighted with the outcome: “Through a long standing and collaborative relationship, Tarmac have developed value added products that enable ELM Surfacing to offer innovative and bespoke designs to our clients. This adds value to the client, contractor, supplier relationship and reduces the impact of the project on local residents whilst delivering the improved infrastructure.” Jake Leyser, Commercial Head of Surfacing at ELM Surfacing.


Learn more about ULTILAYER Download case study

Additional info

Innovative, cost effective approach

The cost effective approach allowed more work to be completed within the budget.

Asset management

Investing in a high performance asphalt would extend pavement life and improve long term value.

Sustainable choice of aggregate 

Durable and carbon neutral steel slag aggregate used in places to replace primary aggregate.

Asphalt contact


ULTILAYER case studies

  • ULTILAYER Durable road surface, A58 Clay Pit Lane
  • ULTILAYER Resurfacing a residential street over poor quality substrates
  • ULTILAYER Preventing reflective cracking and road surface deformation
  • ULTILAYER Fast, single layer resurfacing, Kingston Gyratory re-development
  • ULTILAYER Fast, single layer resurfacing, Stratford Gyratory re-development
  • ULTILAYER Durable resurfacing for concrete overlays,
  • ULTILAYER Durable resurfacing for residential roads
  • ULTILAYER WITH ULTILOW WARM MIX BINDER Fast, sustainable, single layer resurfacing on a busy London road
  • ULTILAYER Junction surface improvements in Cosham, Portsmouth
  • ULTILAYER, ULTILOW and Steel Slag ULTILAYER SMA delivers single layer pavement upgrade in Northolt 
  • ULTILAYER Preventing cracking and deformation on busy city road
  • ULTILAYER Time saving road upgrade to install sustainable cycle-way
  • ULTILAYER Durable asphalt for heavily trafficked city road in central London
  • ULTILAYER Time saving, cost effective asphalt for residential avenue
  • ULTILAYER Preventing repeating cracking on country road
  • ULTILAYER Long lasting asphalt for busy roundabout
  • ULTILAYER Long lasting texture on steep gradient